The Treasury is confronting a KSh109.4bn funding bill to revive and complete four Uhuru-era multipurpose dams after taxpayers have already spent KSh22.6bn on the projects.
The dams – Arror, Kimwarer, Itare and Soin-Koru – were launched under former President Uhuru Kenyatta and have a combined estimated cost of KSh132bn.
By June 2026, Arror had absorbed KSh4.978bn of its KSh38.5bn budget, reaching 13 per cent completion, and required an additional KSh33.522bn.
Kimwarer had spent KSh3.886bn of its KSh33.5bn allocation, achieving 12 per cent completion, with a further KSh29.614bn needed.
Together the two dams had consumed KSh8.864bn, leaving taxpayers facing a further KSh63.136bn to finish them.
Itare Dam had taken in KSh12.066bn of its KSh35bn estimate, reaching 27 per cent completion, and required another KSh22.934bn.
Soin-Koru had used KSh1.67bn of its KSh25bn budget, achieving eight per cent completion, and needed an additional KSh23.33bn.
The State Department for ASALs and Regional Development said the projects are stalled but negotiations to restart them are ongoing.
President William Ruto announced a breakthrough in talks with Italian leaders on reviving Itare Dam and earlier agreements on Arror and Kimwarer, saying “I’m happy that finally we have resolved the issues that were outstanding on some of our projects, Itare project for one. Now we have agreed on how we are going to implement this project going into the future.”
The Itare project’s original contractor, Italian firm CMC di Ravenna, left the site in September 2018; subsequent negotiations produced a settlement that proposes retaining CMC as main contractor while subcontracting construction work.
The financing arrangement for Arror and Kimwarer involved private lenders and Italian state insurer SACE providing default cover.
A technical team appointed during the Kenyatta administration deemed Kimwarer technically and financially unviable, while Arror was allowed to proceed.
Former Treasury Cabinet Secretary Henry Rotich and co-accused were acquitted in December 2023 of the criminal case relating to the two dams.
Soin-Koru is intended to store 93.7 million cubic metres of water, supply 72,000 cubic metres daily, irrigate about 2,570 hectares and generate 2.5 megawatts of electricity.
The combined outstanding financing requirement of KSh109.4bn adds pressure to public finances already strained by debt repayments and competing priorities, according to sector budget proposals for 2027/28.