The World Bank has warned that delays in compensating landowners for the 740 km Isiolo-Mandera Highway could add billions of shillings to the project’s overall cost.
In a letter to Treasury Cabinet Secretary John Mbadi and his counterparts at the Roads and Transport ministry, Davis Chirchir, and the Lands ministry, Alice Wahome, World Bank Kenya Division Director Qimiao Fan said the lack of compensation has stopped contractors from accessing sections of the highway in Wajir and Mandera, slowing construction work.
Fan noted that although the World Bank made funds available for compensation since 2024, the exercise only began in November 2025 and payments have so far been limited to the Isiolo-Modogashe section, with a few residents along those stretches still unpaid.
The bank estimates that restricted access across the six active road contracts is costing the project approximately KSh1.2 billion each month in extra expenses such as private-sector and police and army security, supervision, idle equipment, personnel and site maintenance, and that a further KSh207 million is incurred monthly through demobilisation and remobilisation of construction equipment.
The bank also reported that only 1,281 of the 1,669 approved claimants on the Isiolo-Modogashe stretch have received payments; on the 77 km Isiolo-Kulamawe stretch, KSh456 million has been paid, while delays on the Kulamawe-Modogashe section could add KSh536 million in monthly costs. The Wajir-Tarbaj-Kotulo section is expected to complete compensation by the end of the month, with delays potentially adding KSh421 million each month, and the Kotulo-Elwak stretch could generate an additional KSh243 million in monthly expenses.
The bank warned that ‘prolonged delays could further expose the project to contractual risks, cost escalations and additional implementation setbacks’.