Kenya’s KSh2.1 trillion (approximately $16 billion) Dangote East Africa Refinery in Lamu is confronting environmental, constitutional and financing challenges, according to a policy paper released by the International Policy Group (IPG).

IPG, a Nairobi-based consultancy, argues that the 700,000-barrel-per-day facility could enhance national energy security, cut reliance on imported refined products and position the country as a petrochemical manufacturing and export hub.

The report cautions that unresolved land acquisition, inadequate public participation, water-resource management involving the Tana River and security concerns must be settled before the project proceeds.

A land-compensation lawsuit filed by Lamu residents remains active in the Malindi Environment and Land Court, with the next major hearing scheduled for November 24.

IPG chief executive Kenneth Orengo said that domestic refining capacity could reduce persistent dollar demand, generate thousands of engineering and logistics jobs and anchor industrial infrastructure, but the identified issues must be addressed.

Industry Principal Secretary Juma Mukhwana noted that Kenya’s progressive Constitution permits extensive public participation and that the government must balance safeguards with the need to accelerate economic development, citing the refinery’s fit with the industrialisation agenda and its potential to stimulate coastal industrial parks and special economic zones.

Engineer James Mwangi, an energy consultant and Kenya Private Sector Alliance board member, urged investors to involve Kenyan graduates and technical trainees early through internships rather than waiting until the plant is operational.

Nigerian billionaire Aliko Dangote has projected that the Lamu refinery will create about 60,000 jobs across construction, engineering, logistics and related manufacturing.

The IPG paper warns that a $16 billion refinery could become a stranded asset as global energy systems shift toward cleaner sources, citing International Energy Agency data that renewable electricity capacity is expected to expand by roughly 5,500 gigawatts between 2024 and 2030, with solar and wind accounting for 95 per cent of new additions.

To mitigate that risk, the consultancy recommends fully implementing the planned expansion into polymers, agricultural fertilisers and industrial chemicals to create alternative revenue streams as electric mobility and renewable energy grow.

IPG highlights Lamu’s naturally deep harbour of about 18 metres, which can accommodate large crude carriers without costly lightering, giving it a logistical advantage over regional ports such as Tanga and Mombasa.

The report also advises stronger regional diplomacy and integration through the African Continental Free Trade Area to turn competition into shared industrial growth.

Business Daily Africa reported that the groundbreaking ceremony on September 30, 2026 marked one of Kenya’s largest investments and noted a planned 1,000-megawatt power plant to support the refinery’s industrial ecosystem.

The article added that reliable access to refined petroleum products could strengthen energy security for landlocked neighbours including Uganda, South Sudan and Rwanda and align with the African Union’s ambition to shift from raw-material exports to local value addition.

Dangote recounted challenges faced in Nigeria, such as securing financing, navigating regulatory hurdles and dealing with alleged extortion, warning that unpredictable regulatory environments and unofficial payments could jeopardise the Lamu project.

He set a 40-month timeline for the refinery’s completion, noting that delays could raise financing and construction costs while postponing the anticipated jobs and industrial benefits.

IPG also warned that unresolved historical land grievances and competition over water during recurring droughts could undermine public confidence, delay implementation and fuel conflict, especially as political activity intensifies ahead of the next election cycle.